Dry Run Tests

Test Set Designers can make a test set available for informal test executions by transitioning to the Dry Run workflow state. Reference Workflow Transitions for more information about transitioning workflow states in VERA.

Action Menu Button

Default Role(s)

Test Set Designer

Record Type(s)

Test Sets

Starting Workflow State(s)

Draft

Ending Workflow State

Dry Run

Special Rule(s)

  1. The test set must not have any associated test runs.
  2. After the transition:
    1. Tests can be added to the test set.
    2. Tests can be removed from the test set if the test was not executed.
    3. Tests can be reordered within the test set.
    4. Test set data fields will remain editable.
    5. The test set cannot be transitioned back to Draft.
    6. All tests, regardless of workflow status, can be executed.
  3. For all test runs executed from the test set:
    1. The Draft Run field is set to Y.
    2. The Status field is set to Dry Run.
    3. The Draft Run field cannot be modified.
    4. Dry runs cannot be routed for approval or approved.